Stepan Asia Pte Ltd – Stepan Phase 1 Project
- PROJECT DESCRIPTION
Construction of a five-storey 50,000 tons (expandable to 100,000 tons) per year (“TPY”) Fractionated Methyl Ester (“ME”) plant
Also upgrading of an existing ME plant on Jurong Island.
Works include the addition of tanks, cooling tower, air compressor, fire-fighting facilities
Related facilities involving civil, structural, mechanical, piping, electrical and instrumentation works.
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
- Civil
- Tankage
- Piping & Structures
- Equipment Installation
- Electrical & Instrumentation
CLIENT: Stephan Asia Pte Ltd
LOCATION: Jurong Island, Singapore
OWNER: Stephan Asia Pte Ltd
DURATION: Jan 2011 - Feb 2012
Tank Terminal & Jetty Topsides at Merak (West Java) Indonesia
- PROJECT DESCRIPTION
- Basic engineering followed by the detailed engineering of the tank terminal and jetty topside facilities
- Vertical storage tanks laid out in 4 tank farms
- Total storage facility of 283,500 cbm
- Total of 21 tanks, 2 jetty top site facilities, truck loading facilities, 1 RC main & 4 Containerised S/S
- Tank capacities ranged from 200 cbm to 21,200 cbm
- Products stored include jet fuel, Mogas, Naphtha, MTBE, Gas Oil and Diesel
- Engineering achievement – the site was located within Seismic Zone 4 and all the facilities in the project were designed for seismic loading
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
1. Civil
2. Tankage
3. Piping & Structures
4. Equipment Installation
5. Electrical & Instrumentation
CLIENT: PT Rotary Engineering Indonesia
LOCATION: West Java, Indonesia
OWNER: PT Oiltanking Merak
DURATION: Feb 2008 - Dec 2009
Thai Oil – Khao Bo Ya Crude Tank Farm Legal Reserve Project
- PROJECT DESCRIPTION
- EPC of 5 numbers of tanks with 58 meter ID x 22 meter height, external floating roof single deck
- Supply and install of tank accessories such as breather valves, roof seal, roof drain system, fire water and foam piping system
- Supply and install 3 numbers of tank mixers (side entry) per tank
SCOPE OF WORK:
Engineering Design, Procurement and Construction:
- Civil
- Tankage
- Piping & Structures
- Equipment Installation
- Electrical & Instrumentation
CLIENT: Thai Oil Public Company
LOCATION: Chonburi, Thailand
OWNER: Thai Oil Public Company
DURATION: Mar 2017 - Sep 2018
TOTAL Oil Asia-Pacific – Lube Oil Blending Plant
- PROJECT DESCRIPTION
- 300,000 MTPA lube oil blending plant
- 39 nos. of tanks in the tank farms
- 80,000 DB of piping works, including pipe lines to the shared facility
- Production building, truck loading and unloading bays, office building with parking facilities, miscellaneous buildings and utilities
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
- Civil
- Tankage
- Piping & Structures
- Equipment Installation
- Electrical & Instrumentation
CLIENT: Total Oil Asia-Pacific Pte Ltd
LOCATION: Tuas, Singapore
OWNER: Total Oil Asia-Pacific Pte Ltd
DURATION: Jul 2013 - Jul 2015
Universal Terminal – Crude and Petroleum Storage & its Related Services
- PROJECT DESCRIPTION
- Single phase EPC Project of 2.3 million cbm of Petroleum Storage Terminal Facilities completed in 22 months
- For storage of Crude Oil, Fuel Oil, Lube Oil, Marine Diesel Oil, Gas Oil, Mogas, Naphtha, Jet Fuel
- 70 numbers of Product tanks, including 36 Aluminum Dome Roof Tanks and 34 External Floating Roof Tanks
- 3 numbers of waste water tanks
- Approximately 620,000 diameter-inch of piping works, 45,000 tons of carbon steel plates
- Engineering scope consists of FEED to as-built drawings
- Major achievements in Engineering such as impounding basin design for 6 numbers of 100,000 cbm tanks with optimization of land area done in accordance to code requirements
- Engineering design was done before land reclamation was completed
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
1. Civil
2. Tankage
3. Piping & Structures
4. Equipment Installation
5. Electrical & InstrumentationCLIENT: Universal Terminal Pte Ltd
LOCATION: Jurong Island, Singapore
OWNER: Universal Terminal Pte Ltd
DURATION: Dec 2005 - Oct 2007
Vopak Ethylene Tianjin Terminal Co. – Temparature Ethylene Terminal
- PROJECT DESCRIPTION
- Engineering scope involved the detailed engineering of the facility
- The facility is an ethylene import/ export terminal
- 1 number refrigerated ethylene tank with a storage capacity of 15,000 cbm, ship unloading system and send-out system to the downstream plant
- Ethylene was stored at a temperature of approx -103oC
- The tank was designed as a single containment steel wall with perlite insulation system
- EPC work includes other facilities like control building, substation, etc
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
1. Civil
2. Tankage
3. Piping & Structures
4. Equipment Installation
5. Electrical & Instrumentation
CLIENT: Vopak Ethylene Tianjin Terminal Co. Ltd.
LOCATION: Tianjin, China
OWNER: Vopak Ethylene Tianjin Terminal Co. Ltd.
DURATION: Jul 2003 - Jul 2005
Vopak Shanghai Logistics Co. – Vopak Multi Product Terminal
- PROJECT DESCRIPTION
- Total of 62 numbers of chemical storage tanks of CS and SS material
- EPC work includes truck loading bay, drum filling room, pipe racks and jetty topsides
- Detailed engineering work for tankage, civil, equipment sizing, piping, electrical and instrumentation works
- Procurement of tank farm equipment such as steel plates, piping materials, electrical cables, instrument tubing, instrument gauges, pumps and motors etc
- Equipment works include installation of ship loading pumps, gangways, marine loading arms, fire monitor tower, jetty jib
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
1. Civil
2. Tankage
3. Piping & Structures
4. Equipment Installation
5. Electrical & Instrumentation
CLIENT: Vopak Shanghai Logistics Co. Ltd
LOCATION: Shanghai, China
OWNER: Vopak Shanghai Logistics Co. Ltd
DURATION: Jan 2003 - Dec 2006
XSBR Project – Mechanical, Piping, Electrical & Instrumentation Works
- PROJECT DESCRIPTION
Mechanical & Piping Works:
- To provide scaffolding for equipment and piping installation as necessary.
- Supply and installation of holding down/ anchor bolts, studs, washers and nuts where not provided but deemed necessary for installation of equipment piping and structures on concrete foundations/plinths.
- Shop/Field fabrication or modification, erection, testing and painting of new pipe works.
- Supply material, fabricate, galvanizing, and erection of pipe supports.
Electrical Works:
- Motor starter
- Motor Control Station (MCS)
- Power Supply for Pumps, Package Unit and Lighting & Power Distribution Board
- Cable Supply & Installation
- Cable Tray/Ladders Supply & Installation
- Cable Termination
- Grounding
- Testing and Commissioning
Instrumentation Works:
- Control Panel In DCS room
- Instrument Installation
- Junction Box Installation
- Cable Tray/Ladder Installation
- Cable Installation and Termination
- Instrument Earthing and Bonding
- Instrument Air Header and Tubing Installation
- Relocation of Existing Instruments
Inspection and Testing
SCOPE OF WORK:
Construction Services:
- Mechanical & Piping
- Equipment Installation
- Electrical & Instrumentation
CLIENT: Synthomer Sdn Bhd
LOCATION: Johor Bahru, Malaysia
OWNER: Synthomer Sdn Bhd
DURATION: Feb 2015 - Jul 2015
BP Zhuhai Rock Cavern Project
- PROJECT DESCRIPTION
EPC for 2 full containment underground LPG storage caverns in BP Phase 2 Expansion
Capacity of each cavern was 200,000 cbm
REL prepared and developed all LPG storage cavern mechanical engineering documentation. Scope included definition of piping, valve, instrument, electrical and control interfaces
All design calculations as required by codes, standards and documents as specified in the ITT and Functional Specification for the LPG Caverns shown in the drawings and specifications
General arrangement drawings, including details of openings, nozzle orientations, cavern sumps etc. Fabrication drawings, fabrication, transport, and installation procedures
REL performed a cavern repair and reinstatement portion in the later part of the project, due to mistakes by client’s underground contractor resulting in incomplete grouting of cavern plug. This involved dismantling casing within Butane shaft / down-hole sump area in preparation for the Cavern’s grouting repair works. This is a dangerous undertaking due to a confined space entry and the only point of entry is top-down
SCOPE OF WORK:
Engineering Design, Procurement & Construction:
- Civil
- Tankage
- Piping & Structures
- Equipment Installation
- Electrical & Instrumentation
CLIENT: Zhuhai JVO Arco Energy Co. Ltd
LOCATION: Zhuhai, China
OWNER: Zhuhai JVO Arco Energy Co. Ltd
DURATION: 2003 - 2006