- Total of 11 tanks, including shop fabrication and site erection. Tank materials are CS, SS and duplex
- Total of 117,126 DB of piping fabrication and erection works
- Installation of 36 equipment totalling 207 tons
- Electrical & instrumentation works include grounding and lighting, installation of substation, cable tray, cable ladder, CP protection and heat tracing systems
Project Type: Process Plant
Shell Mono Ethylene Glycol (MEG) Plant
- 200,000 DB shop fabrication & field installation of pipes
- Pipe sizes ranging from 2” to 88”
- Equipment installation of 480 nos. ranging from 2 tons to 1,200 tons
Shell Mono Ethylene Glycol (MEG) Plant
- EPC works for 750,000 cbm TPA Mono Ethylene Glycol (MEG) downstream plant in Jurong Island
- Scope of work include mechanical construction, piping & equipment installation
- Shop fabrication & field Installation of estimated 200,000 DB of pipes
- Pipe sizes range from 2” to 88”
- Equipment installation of 486 nos. ranging from 2 tons to 1,200 tons
- Engineering lifting studies for heavy lifts & piping spoolgen drawings for shop fabrication
Singapore Parallel Train
Electrical works:
- Utility Substations with MV Transformers & LV Transformers
- Air Cooler & Olefins Substations with MV Transformers & LV Transformers
- 120MW Gas Turbine Generators (GE Make) with 150MVA GSU Transformers
- Auxiliary Transformers & Iso-Phase Bus Duct System
- GTG Migration
- GLAC Erection/Installation Check
- GNAC Erection/Installation Check
- MV Motors (6.6kV) & LV Motors (433V)
- MV & LV Switchgears
- MCCs & Distribution Panels
- Plant Lighting & Power System
- Cathodic Protection System
- Electrical Heat Tracing System
- Cable Ladder / Tray System
- UPS System / Battery
- Grounding System
- Standby Generator
- Substation System
- Preservation
Instrumentation works:
- Instrument Cable System
- Air Supply Tubing System
- Loop Foder / Assembly Procedure
- RIE Installation
- Analyzer Container Installation
- Instrument Calibration
Singapore Parallel Train
Mechanical, structural & piping package
- 337,000 DB piping fabrication & erection
- 7,900 tons of steel structure erection
- 127,000 DB small bore fabrication
- 667 units of equipment installation
- Underground piping works include excavation, backfilling, concrete & steel bar reinforcement
Singapore Parallel Train
- 337,000 DB piping fabrication & erection works
- 7,900 tons of steel structure erection
- 127,000 DB of small bore fabrication works
- 667 units of equipment installation
- Underground piping works including excavation, backfilling, concrete & steel bar reinforcement
- Electrical & instrumentation works