[ page 1 ] [ page 2 ] [ page 3 ] [ overseas projects ]

Crude AMF Modification Project

  Client : Toyo Engineering Corporation


Owner: Lonza Singapore Pte Ltd

Construction Period : April 2001 to January 2002
 

 
Scope of Work : Engineering Services, Construction and
Shutdown tie-in of Mechanical and E&I works
 
Location : 12 Sakra Road, Jurong Island, Singapore
 

BRIEF DESCRIPTION:

Engineering design, procurement and construction of process piping works.
Engineering design, procurement and construction of electrical and instrumentation works.
Engineering design and construction of civil foundation, inclusive of micro-piling, and
anti-acid coating works.
Heavy haulage, equipment installation works in live plant environment.
Modification of existing structural support for new filter unit, inclusive of painting works.
Fabrication and erection of piping, inclusive of pipe supports, scaffolding, painting and
insulation works.
Shutdown tie-ins, vessel nozzle modification works.
Power and control cables laying, instrumentation termination.
Pre-commissioning and start-up support

 

 

Shutdown Maintenance Project

  Client : Rotary Brown & Root Pte Ltd


Owner: Eastman Chemical Singapore Pte Ltd

Construction Period : Aug 2002 to Sept 2002
 

 
Scope of Work : Planning, Scheduling, Coordinating of Shutdown activities.
  
Location : 3 Seraya Avenue
 

BRIEF DESCRIPTION:

Planning, scheduling, coordinating of pre-shutdown and shutdown activities.
Tagging, removal of safety relief valves, control valves for servicing and thereafter,
reinstate.
Tagging, removal of motor for servicing and thereafter, reinstate, leveling and laser
alignment.
Removal of vessel covers for cleaning and inspection, and reinstatement thereafter.
Removal of exchanger channel head for bundle pulling for cleaning and inspection, and
thereafter reinstate.

 