Rotary Engineering Limited

Projects Showcase

Chemical

Phase 2A Project - Map Ta Phut

Phase 2A Project - Map Ta Phut

Client:

Thai Tank Terminal Limited

Owner:

Thai Tank Terminal Limited

Construction Period:

January 1994 to January 1995

Scope of Work:

Civil, tankage, piping, mechanical equipment installation, E & I works

Location:

Thailand

Brief Description:

  • Civil, tankage, piping, mechanical equipment installation, electrical and instrumentation works.
  • Detailed engineering design, procurement, fabrication and construction of roof tanks.
  • Civil work consists of construction of building and tank foundations.
  • Installation and supply of mechanical equipment.
  • Construction and installation of electrical sub-station and changing of the existing high voltage cables from above ground to underground.
  • Installation of instrumentation system